Industry2026-09-03
BMS and inverter pairing: agree the point list early
Most residential storage delays at commissioning come from an unmatched protocol, not from the battery.

A battery cabinet can arrive complete and still fail commissioning because the inverter expects a different protocol or register set. The fix is procedural: agree the point list and the protocol version before the cabinet is built.
Our quotation now asks for the inverter model and firmware version, and the pairing sheet is issued with the order.
Need the document referenced in this article?
Datasheets and manuals are listed in the download centre. Gated files are released on request so that revision changes can be tracked.